Status 03/31/08:

 

RESEARCH/GENERAL

¡         Specs – All specs are completed with the exception of the conditions for the approval routings. These pieces should be completed early in the next week. There may be a table added to aid in the conditional routing (around job code – may be able to utilize a table that was already created).

 

¡         Development – Forms have all been developed and now need testing and tweaking, which will occur through this test phase and the next one.

 

o         Development continuing for alternate approver selection.

o         Issue log being used to note problems or changes needed in forms.

o         Development around department routing (routing to Org Head 1 and Org Head 2, etc) has been completed. This can now be tested.

o         I-9 being placed in environment for testing

o         Payroll SQR modified to pause ePAF transactions (just the save piece, not the approval routing) during payroll and to un-pause after confirm.

 

¡         Mid-stacks – there was a lot of conversation through the week around how to handle mid-stack transactions. (Transactions which must be inserted before an existing transaction in an employee’s history. For example, a retro termination is sometimes done and must be inserted prior to a distribution change that was already entered.)

o         Original Mid-stack logic left holes that needed to be addressed

o         In addressing the holes, we realized that a very robust approach would be needed in order to cover every situation identified

o         We have pulled back the idea to cover basic scenarios. Additional work can be done in future enhancements to make the logic robust and cover all situations.

 

 

¡         Testing Discoveries – As forms are being tested and issues are identified, they are tracked in the UU_Tracking_Log. See log for details around all testing issues.

o         Changed all email addresses in HRWILD to point to uuepaf@gmail.com to ensure no users outside of the project group get testing emails

o         In DEV and Test, we will only change email addresses for those users who are found on UU_HR_ROLE_DEPT

o         During training, the email script for DEV and Test will be used, but it will need to be run daily.

 

 

DESIGN

Spec Design : Change of Employment Status – 100% Complete

  

Spec Design : New Hire Form – 100% Complete

 

 Spec Design : Job Change Form – 100% Complete

  

Spec Design : Employee Personal Data Form – 100% Complete

 

 Spec Design : Manual Request Form – 100% Complete

 

 Spec Design : UU Roles to LDAP Translation – 100% Complete

  

Spec Design : Manage Personal Workflow Form – 100% Complete

 

 Spec Design : I-9 – 100% Complete

 

 

Spec Design : Approval Routing – 85% Complete

PLANNED

o         Complete routing conditions

o         Bring in I-9 form

o         Gather difficult test scenarios for testing

o         Create the faculty approval paths in environment

o         Testing :

§          Org Head Routing

§          Faculty Routing

§          I-9

§          All forms – continued testing and tweaking

o         Re-test of cleaned up issues